Trout Lake Road Overpass Delays Tuesday

North Bay, ON – November 6, 2017 – Due to the completion of the Stage 1 works, traffic will now be redirected to the north side of the bridge to allow commencement of the south side works. Switch over of the traffic will take place on Tuesday, November 7, 2017. Motorists are to expect delays during this short duration of time and are encouraged to use an alternate route.

 

The City of North Bay thanks residents for their continued understanding and patience while this important infrastructure work is being completed. The project is anticipated to be substantially completed for late December of this year where all four (4) lanes of traffic will be operational.

 

 

The City of North Bay is a city of 54,000 people situated between the shores of Lake Nipissing and Trout Lake. For information on City services and programs, North Bay residents, businesses and visitors can visit www.cityofnorthbay.ca