Cassells Street Reconstruction Gets Underway

North Bay, ON – July 12, 2019Reconstruction of Cassells Street between King Street and Highway 11/17 gets underway next week.

Kenalex Construction Company Limited has been selected to complete the project, valued at $10.9 million, plus HST, as part of a public procurement process.

"This extensive work will result in safer, more fluid travel for residents and visitors and will ultimately help local businesses on a major arterial road leading into the downtown,” said Coun. Chris Mayne, Chairman of Council’s Infrastructure and Operations Committee. "We’re continuing to focus on maintaining and improving City infrastructure, ensuring residents see that their tax dollars are well spent.”

The work includes four travel lanes between King and Olive streets, five travel lanes between Olive Street and Highway 11/17, along with various turn lanes and access upgrades, as well as sidewalks, curbs and gutters on both sides.

The project will see traffic signals at Chippewa and Olive streets replaced, reconstruction of Shaw Street and improvements to the Victoria Street intersection. Sanitary and storm sewer systems will also be replaced, along with the water distribution system.

The Cassells Street bridge will be replaced, including rehabilitation of Chippewa Creek on both sides of the new structure. All disturbed areas will be restored.

According to the preliminary schedule, construction of Phases 1 and 2 from King Street to Chippewa Street are anticipated to be complete by Nov. 25, 2019. Construction of Phase 3 and 4, from Chippewa to Highway 11/17, is to be completed by Nov. 15, 2020

A public information open house will be held July 15, 2019 from 4:30 p.m. until 6:30 p.m. in the main lobby at City Hall featuring various drawings detailing construction and associated traffic control. The City of North Bay and Kenalex Construction will have representatives on hand to answer questions and review concerns.

As construction proceeds, additional public notices will be issued to provide updates on the project’s schedule and progress.